Montrose Green Infrastructure (Raingarden & Permeable Pavement) Pilot Project. Launch!!
We at Community In Power Development Association Inc. have some exciting new updates surrounding our Montrose Green Infrastructure and...
Dec 5, 2023


Montrose Green Infrastructure (Raingarden & Permeable Pavement) Pilot Project. Phase: Rock Layer
We have exciting new updates surrounding our Montrose Green Infrastructure Project. In our last update we discussed the monumental moment...
Feb 24, 2023


Montrose Green Infrastructure (Raingarden & Permeable Pavement) Pilot Project. Phase: Excavation
CIDA has very exciting news and updates! Monumental history has been made in Port Arthur, Texas. We have officially broken ground at...
Dec 15, 2022


Montrose Park Green Infrastructure Update
Our partnered Montrose Green infrastructure project is making tremendous progress in moving forward. We have been granted the approval...
Sep 8, 2022


Montrose Green Infrastructure Site Visit
On November 11th, 2021 we had the opportunity of partnering and meeting with Montrose community residents. We took a community led tour...
Feb 11, 2022